Factory Acceptance Test (FAT) for a Production Line: Buyer’s Checklist

Short answer: A factory acceptance test (FAT) is a test of your production line or machines at the supplier’s factory before they are packed and shipped. Its purpose is to prove, against criteria written in the contract, that the machines you ordered are complete, built as specified and run correctly with your product or containers. Agree the test protocol and acceptance criteria before you sign, attend in person, by live video or through an independent inspector, record the results in a signed report, and allow shipment only after the issues found have been fixed and checked again.

This guide is for investors, factory owners and project managers in the Arab countries, the Middle East and Africa who are buying a production line, often from China. It explains what a FAT covers, how it differs from the site acceptance test (SAT) after installation, and what to agree in writing. It does not give fixed test durations or costs, because they depend on the line, the number of machines and the test conditions agreed with the supplier.

Read also: How to Choose a Production Line Supplier in China · Shipping and Customs Clearance · Factory Site Preparation · النسخة العربية · All guides

FAT and SAT: what is the difference?

Factory acceptance test (FAT)Site acceptance test (SAT)
WhereAt the supplier’s factoryAt your factory, after installation
WhenAfter manufacturing, before packing and shippingAfter installation and commissioning
PurposeConfirm the machines are complete, built as specified and run as agreed before they leaveConfirm the line works in your building with your utilities, product and operators
Who attendsThe buyer or their representative, in person or by live video, or an independent inspectorThe buyer’s team and the supplier’s engineers
ResultA signed FAT report and a list of issues to fix before shippingA signed SAT report and the start of the agreed warranty, if the contract links them

Both tests matter. A FAT finds problems while the machines are still at the factory, where they are easier to fix. A SAT confirms the result in real conditions after shipping and installation.

What to agree in the contract before the FAT

  • Test protocol: which machines are tested, which functions are checked and how results are recorded.
  • Acceptance criteria: the measurable results the line must reach, taken from the contract and the technical offer, for example the agreed output and the quality of the finished product.
  • Test materials: who provides the product, containers, caps, labels, film or raw material for the test, and how samples are shipped to the supplier.
  • Attendance: whether you attend in person, by live video or through an independent inspection company, and who pays the travel or inspection costs.
  • Notice: how much notice the supplier gives before the test date.
  • Failure and retest: what happens if the test fails, how issues are fixed and when the retest takes place.
  • Link to payment and shipping: whether a payment milestone and the shipping date depend on a passed and signed FAT.

FAT checklist

AreaWhat to check
Scope of supplyEvery machine, option and accessory in the contract is present, with the agreed models, and nothing is missing.
Build and materialsDimensions, finish and the materials of parts that touch the product match the technical offer.
Electrical and controlsControl panel, wiring and the brands of key components such as PLC, touch screen, motors and drives match what was quoted. The control language and voltage match your requirements.
SafetyGuards, emergency stops and interlocks are fitted and work.
Running testThe line runs with your product or containers, or the substitutes agreed in the contract, at the conditions in the test protocol. Record the measured output and stops.
Product qualityThe finished product meets the agreed criteria, such as fill level, weight, capping, sealing, labelling or part dimensions, depending on the line.
ChangeoverChanging between your container or product sizes works as agreed, and the change parts are supplied.
DocumentsOperating and maintenance manuals, electrical drawings, layout and spare parts list are delivered.
Spare parts and toolsSpare parts and tools in the contract are present and listed for packing.
Packing readinessPacking method and crate marking are agreed, so the machines tested are the machines shipped.

What to test by sector

SectorPoints to include in the test
Water and beverages (Servolines)Rinsing, filling and capping with your bottles, caps and labels; fill level and cap tightness; changeover between bottle sizes.
Bakery and pastry (Ferrni)Running the machines with dough or product made to your recipe or an agreed equivalent; shape, weight and appearance of the products.
Animal feed (Renfoo)Running the main machines with the raw material agreed for the test where practical; the form of the finished feed against the agreed criteria.
Plastics (Renplas)Producing sample parts with your mould or the supplied mould; part dimensions and appearance against your drawing or sample.
Packaging (Niopac)Running with your product and packaging material; weight or count accuracy, bag or carton quality and sealing.
Metal working (Eirmac)Cutting or bending sample parts from your drawing and material; checking dimensions against the drawing.

The exact test for your line is set in the protocol agreed with the supplier. Where your own material cannot be shipped for the test, agree a substitute in writing.

Attending in person, by video or through an inspector

Attending in person lets your team see the machines and learn them early. If travel is not practical, a live video test can work when the camera follows the protocol step by step and the results are recorded. An independent inspection company is another option; give it the contract, the technical offer and the protocol so that it checks against the same criteria.

After the test: report, punch list and shipping

  • Sign a FAT report that lists what was tested, the results and every open issue.
  • Agree a punch list with an owner and a fix date for each issue.
  • Check the fixes before shipping, by retest, video or photos, as agreed.
  • Confirm that the tested machines are packed according to the agreed method and packing list.
  • Keep the FAT report for the site acceptance test after installation.

What to send for a quotation

  • Your product, required output and the machines you are interested in.
  • Your containers, packaging or materials, with photos or samples if possible.
  • The quality criteria that matter most to you.
  • Whether you want to attend the FAT in person, by video or through an inspector.
  • Your country, utilities (voltage and frequency) and the control language you need.

Common mistakes

  • Signing without a written test protocol and acceptance criteria.
  • Testing without your own product or containers, or an agreed substitute.
  • Making the shipping payment before the FAT is passed and signed.
  • Accepting a test that only shows the machines running empty.
  • Not recording the results and open issues in a signed report.
  • Not checking that the spare parts, change parts and documents are ready to ship.

How Rendat helps

Rendat is an industrial machinery group based in Yiwu, China, supplying production lines and machines through its brands: Servolines for water and beverages, Ferrni for bakery and pastry, Renfoo for animal feed, Renplas for plastics, Niopac for packaging and Eirmac for metal working, with spare parts through RendatSP. We start from your project data and provide an itemised proposal. The pre-shipment test arrangements for your line are set out in the quotation and the contract.

FAQ

What is a factory acceptance test (FAT)?

A FAT is a test of the production line or machines at the supplier’s factory before shipping, to confirm against agreed criteria that they are complete, built as specified and run correctly.

What is the difference between FAT and SAT?

The FAT is done at the supplier’s factory before shipping. The site acceptance test (SAT) is done at your factory after installation, with your utilities, product and operators.

Do I have to travel to China for the FAT?

No. You can attend in person, follow a live video test or appoint an independent inspection company. Agree the method and who pays for it in the contract.

What should I send to the supplier for the test?

Send samples of your containers, caps, labels, packaging or raw material, as relevant to your line, or agree a substitute in writing if your own material cannot be shipped.

What happens if the machines fail the FAT?

The issues are recorded in the FAT report, the supplier fixes them, and they are checked again before shipping, according to the retest terms in the contract.