Short answer: Prepare the factory site before the machines ship, not when the containers arrive. Fix the final line layout with your supplier first, then get the building, floor, power supply, water, compressed air, drainage and ventilation ready to match that layout and the supplier’s utility list. Clear a route for containers and lifting equipment, assign who does what in writing, and send the supplier photos and drawings of the finished site before the installation team travels. Most installation delays come from site work that was not finished, not from the machines.
This guide is for investors, factory owners and project managers in the Arab countries, the Middle East and Africa who are installing a new production line, whether for water and beverages, bakery, animal feed, plastics, packaging or metal working. It is general buyer guidance; the exact utility figures, foundation details and floor space for your line come from the supplier’s layout drawing and technical documents for each project.
Read also: Production Line After-Sales Service · How to Choose a Production Line Supplier in China · النسخة العربية · All guides
Step 1: Agree the line layout before any building work
Ask the supplier for a layout drawing based on your actual building dimensions, and do not pour floors, trench drains or run cables until it is agreed. The layout should show every machine, conveyors, control cabinets, utility connection points, operator walkways, maintenance access around each machine, and storage areas for raw materials, packaging and finished goods. Plan the flow in one direction where possible: raw materials in, finished goods out, without crossing paths.
Step 2: Building and floor
- Clear height and openings: check that the tallest machine, silo or conveyor fits under beams and lights, and that doors are wide and high enough to bring machines in.
- Floor: the floor must be level and strong enough for the machine weights and any vibration. Ask the supplier which machines need a foundation, anchor bolts or a specific floor finish, and follow their drawing.
- Hygiene zones: food and beverage plants usually need washable floors and walls, floor drains with suitable slopes and separated clean areas. Check what your local food safety authority requires.
- Space for expansion: if you plan a second line or a higher output later, keep space and utility capacity for it now.
Step 3: Utilities checklist
Every line has its own utility list. Use the table to confirm each item with the supplier and your local contractor; the actual values are those in the supplier’s technical documents.
| Utility | What to confirm with the supplier | Typical site preparation |
|---|---|---|
| Electrical power | Total connected load, voltage, frequency and phases for every machine | Transformer or supply capacity, main panel, cable routes to each control cabinet, earthing |
| Water | Process water, cleaning water and cooling water needs, and any quality requirement | Supply pipe to the connection points, storage tank, treatment if required |
| Compressed air | Air consumption, pressure and air quality (dry, oil-free where needed) | Compressor room, dryer and filters, piping to each machine |
| Steam, gas or heating | Whether ovens, boilers, conditioners or dryers need gas, diesel, steam or electric heating | Fuel supply, boiler room, permits and safety approvals |
| Drainage | Wastewater, cleaning water and other discharge points | Floor drains, trenches and a legal discharge route |
| Ventilation and cooling | Heat from ovens, motors and compressors; dust or fumes from the process | Exhaust fans, extraction, chillers or cooling towers if required |
| Lighting and safety | Areas that need inspection lighting or protected fittings | Lighting, fire safety, emergency exits |
Step 4: Access, delivery and lifting
- Check the road and gate access for container trucks and the space to park and unload them on site.
- Plan who provides the forklift, crane or rollers to unload and move each machine, and confirm the heaviest piece with the supplier.
- Prepare a dry, secure area to store crates until installation starts.
- Keep the installation area clear of other construction work when the installation team arrives.
Step 5: Documents to send to the supplier
- Building drawing with dimensions, column positions, door sizes and clear height.
- Photos and a short video of the empty building and the finished floor.
- Details of the local power supply (voltage, frequency, phases) and the available capacity.
- Your water source and, for water and beverage plants, a laboratory water analysis.
- Product samples or specifications and the containers or packaging you will use.
- Any local rules that affect the design, such as food safety, electrical or fire codes.
Step 6: Typical timeline steps
Durations depend on the project, the country and how fast the site work is done, so agree the schedule in the contract. The usual sequence is:
- Agree the layout drawing and the utility list.
- Building and civil work: floor, foundations, drains, openings.
- Utilities: power, water, compressed air, heating and ventilation brought to the connection points.
- Machines manufactured and tested at the supplier where agreed, then shipped.
- Delivery, unloading and positioning of the machines.
- Installation, connection to utilities and commissioning with your product.
- Operator and maintenance training, then handover and acceptance.
Table: who usually does what
Responsibilities vary by contract; this is a common split to discuss and then fix in writing.
| Task | Usually the buyer | Usually the supplier |
|---|---|---|
| Layout drawing | Provides building dimensions and approves | Prepares the line layout and utility points |
| Building, floor and foundations | Builds to the supplier’s drawing | Gives loads, foundation and anchor details |
| Utilities to connection points | Supplies power, water, air, drains and heating | Lists the required utilities for each machine |
| Unloading and lifting | Provides cranes, forklifts and labour on site | Advises on weights and lifting points |
| Installation and commissioning | Provides helpers, materials and product for testing | Supervises or installs as stated in the quotation |
| Permits and local approvals | Obtains them | Provides machine documents needed for the application |
| Training and handover | Assigns operators and maintenance staff | Trains and provides manuals and drawings |
Common mistakes
- Building the floor or drains before the layout drawing is agreed.
- Underestimating the power supply or compressed air needed once every machine is running.
- Forgetting door height or clear height for the largest machine.
- No plan for unloading the containers, so crates wait outside.
- Leaving responsibilities unwritten, so each side expects the other to supply cables, pipes or lifting equipment.
How Rendat helps
Rendat is an industrial machinery group based in Yiwu, China. Its brands cover each sector: Servolines for water and beverages, Ferrni for bakery and pastry, Renfoo for animal feed, Renplas for plastics, Niopac for packaging and Eirmac for metal working, with spare parts through RendatSP. With each quotation we can provide a line layout and the utility requirements for the proposed machines, so you can prepare the site in parallel with manufacturing; installation, commissioning and training are set in the quotation for each project.
Sector guides: bottled water plant · water treatment · automatic bakery · feed mill · plastic machines · packing machines · fiber laser and press brake.
FAQ
When should I start preparing the factory site?
As soon as the line layout and utility list are agreed with the supplier, so that building and utility work runs in parallel with machine manufacturing.
Who prepares the floor and foundations?
Usually the buyer, working to the supplier’s layout and foundation drawings. Confirm the split of responsibilities in the contract.
What utilities does a production line need?
Most lines need electrical power, compressed air and water; many also need drainage, ventilation, and gas, steam or heating. The exact list and values come from the supplier’s technical documents.
What should I send the supplier before installation?
Building drawings with dimensions, photos of the finished site, local power supply details, your water source and product or packaging details, and any local rules that affect the design.
Does Rendat provide installation and training?
On-site installation and operator training are part of Rendat’s services; their scope and details are set in the quotation for each project.
Request a layout and quotation
Send us your product, target output, country and building drawings, and we will propose a line with its layout and utility requirements. Request a quote or WhatsApp +86 181 5871 1787.